ROLE
OCR
BUDGET
$11.0 million
COMPLETED
2017

Major renovation to existing Memorial Stadium including new 10 lane track successfully completed in just 5 months. Challenging soils necessitated a major excavation and state-of-the-art drainage system.

GREAT FALLS PUBLIC SCHOOLS STADIUM CASE STUDY

Managing A Tight Timeline and Complicated Soil Structures for a Successful Stadium Renovation

Identified in the 2016 GFPS School Bond, Memorial Stadium underwent a major renovation during the summer of 2017. Design and construction were completed in just 5 months, with the facility ready for use in September that year. The field sits on a major over excavation due to extremely expansive soils in the area, necessitating a state-of-the-art drainage system. Since opening, the District has hosted numerous Shrine Games, as well as state level track and field competitions on the new 10 lane track. Hulteng CCM’s experience in project procurement methodology was critical to achieving a successful outcome on an extremely tight timeline.